Used and remanufactured pad mounted transformers
When new units are a year out, a remanufactured transformer is a legitimate answer and utilities buy them routinely. It is only a bad idea when nobody can show you the test reports.
Test reports to demand before you pay
- Dissolved gas analysis. Reads the oil for the by-products of internal arcing and overheating. This is the single most informative test on a used unit.
- Oil quality. Dielectric strength, moisture, acidity. Tells you whether the fluid is serviceable or needs replacing.
- Turns ratio, on every tap. Confirms the windings are intact and the taps actually work.
- Insulation resistance and power factor. The condition of the insulation system, which is what ultimately fails.
- PCB screen if built before 1979. Non negotiable. A contaminated unit is a disposal liability, not an asset.
A photograph of the nameplate plus a current dissolved gas analysis tells you more about a used transformer than any description a seller writes. If a seller will not provide both, that is the answer.
New against remanufactured
| New | Remanufactured | |
|---|---|---|
| Lead time | 40 to 60 weeks | Days to weeks |
| Price | Full | Typically 50 to 70 percent |
| Efficiency | Meets DOE 2016 | Often pre-2016, higher losses |
| Warranty | Usually 12 to 24 months | Usually 12 months from the remanufacturer |
| Records | Factory test report | Only as good as the shop that did it |
The efficiency line is the one people skip. A pre-2016 unit burns the saving back over a thirty year life, so a remanufactured transformer is strongest when the driver is the date rather than the budget.
Who remanufactures