MVA transformers, 1 to 100 MVA

An MVA transformer is a power or substation transformer rated in megavolt amperes, 1 MVA being 1,000 kVA. Below is every common size from 1 to 100 MVA with its full load current at six voltages, what a stacked rating such as 12/16/20 MVA means, the published price benchmarks and today's lead times. We source new, surplus and used units in this range and quote them delivered.

Standard MVA sizes with full load amps

Full load current for a three phase transformer is MVA x 1,000,000 divided by (1.732 x line voltage). Every figure below is computed that way, so read the column for the winding you are sizing. Units up to about 10 MVA are often built as large pad mounted or unit substation transformers, while the larger sizes are substation power transformers with a 34.5, 69 or 138 kV primary.

MVAkVAAmps at 4.16 kVAmps at 12.47 kVAmps at 13.8 kVAmps at 34.5 kVAmps at 69 kVAmps at 138 kV
11,0001394642178.44.2
1.51,500208696325136.3
22,000278938433178.4
2.52,500347116105422110
33,000416139126502513
3.753,750520174157633116
55,000694231209844221
7.57,5001,0413473141266331
1010,0001,3884634181678442
1212,0001,66555650220110050
1515,0002,08269462825112663
2020,0002,77692683733516784
2525,0003,4701,1571,046418209105
3030,0004,1641,3891,255502251126
4040,0005,5511,8521,673669335167
5050,0006,9392,3152,092837418209
6060,0008,3272,7782,5101,004502251
7575,00010,4093,4723,1381,255628314
100100,00013,8794,6304,1841,673837418

Computed values, rounded to the nearest amp. Use the kVA to amps calculator for any other voltage.

Stacked ratings, 12/16/20 MVA and ONAN, ONAF

Many substation transformers carry two or three ratings on one nameplate. The first number is the self cooled rating, oil natural and air natural, written ONAN (formerly OA). Each higher number is the rating with a stage of cooling fans running, written ONAF (formerly FA). A 12/16/20 MVA unit carries 12 MVA with no fans, 16 MVA with the first set of fans and 20 MVA with both sets.

Two things follow. The percent impedance on the nameplate is normally stated on the self cooled base, so check the base before you run fault studies. And a 12/16/20 unit is not a 20 MVA unit in a hot climate if a fan stage is out. Size the load against the stage you can rely on.

RatingCoolingAmps at 13.8 kVAmps at 69 kVAmps at 115 kV
12 MVASelf cooled, ONAN50210060
16 MVAFirst fan stage, ONAF66913480
20 MVASecond fan stage, ONAF837167100

Example of a 12/16/20 MVA nameplate. Amps computed from MVA and voltage.

MVA transformer prices

Power transformer prices are quoted per unit, not from a list, and they move with steel, copper and the order book. These are published benchmarks, not our prices. A quote from us is a delivered price for a specific unit.

BenchmarkFigurePublished by
New large power transformer procurement price$15,000 to $21,000 per MVANextMSC, citing USITC data via NLR
100 MVA unit at that benchmark$1.5 million to $2.1 millionNextMSC calculation
Highly customized 100 MVA unitUp to about $4 millionNextMSC, citing NLR
Upper single unit benchmarkAbout $10 millionNextMSC, citing USITC via NLR
Average declared value of US imports above 100 MVA, 2025About $1.22 million a unitNextMSC, from import data for liquid dielectric transformers above 100,000 kVA

Benchmarks are for large power transformers. Smaller MVA units are quoted per job and are not a straight multiple of these figures.

Lead times by class

Lead time, not price, is what decides most projects in this range. Wood Mackenzie's survey for the second quarter of 2025 put the average power transformer lead time at 128 weeks, about two and a half years, after a 10 week improvement in that quarter. Generator step up units averaged 143 weeks. Some specialized orders run to four years.

Wood Mackenzie also expected a 30 percent supply shortfall for power transformers in the US in 2025, with imports making up an estimated 80 percent of US power transformer supply. That is why surplus, used and reconditioned units and cancelled order slots are worth asking about in this size range.

EquipmentTypical lead timePublished by
Power transformers, average128 weeks (Q2 2025)Wood Mackenzie, via Industrial Sage and Giga Energy
Generator step up transformers, average143 to 144 weeks (Q2 2025)Wood Mackenzie, via Industrial Sage and NextMSC
Large power transformers, current30 to 36 monthsNextMSC, citing NLR
Large power transformers, before the shortage12 to 18 monthsNextMSC, citing NLR
Extra high voltage transformersUp to 60 monthsNextMSC, citing DOE and NLR
High voltage bushingsUp to about 130 weeksNextMSC
On load tap changersAbout 80 to 90 weeksNextMSC
Switchgear, average44 weeks (Q2 2025)Wood Mackenzie
Three phase pad mounts for data centers40 weeks and more, per EPC quotesGiga Energy

What moves the price and the date

Wood Mackenzie reported electrical steel prices rising more than 20 percent in a few months of 2025, which moves contracts that carry a price adjustment formula, and named winding grade copper as a production bottleneck. New tariffs, including a 50 percent tariff on copper from August 2025, push up both imported and domestically built units. Expect a quote in this range to carry a validity period and a metals adjustment clause.

New US capacity is coming, but late. Hitachi Energy broke ground on a $457 million expansion in South Boston, Virginia in June 2026 and plans a $528 million plant in Mississippi with production in 2029, according to NextMSC.

Weight and footprint

Weight and footprint vary too much by voltage class, impedance, cooling and the maker to publish one range per size, and we did not find a public source we trust that does. Ask for the outline drawing with any quote. It gives the shipping weight, the oil volume, the untanking weight and the pad dimensions you need for rigging, transport permits and the foundation.

What to send for a quote

  • MVA rating, and the stacked ratings if you need fan stages, for example 12/16/20 MVA ONAN/ONAF/ONAF
  • Primary and secondary voltage, for example 69 kV delta to 13.8Y/7.97 kV, and the BIL if your utility specifies it
  • Percent impedance, especially if you are matching or paralleling an existing unit
  • Tap changer, de energized taps or an on load tap changer
  • New, surplus, used or reconditioned, and the factory tests you need on paper
  • Site ZIP code and the date you need it energized

Common questions

What does MVA mean on a transformer

MVA is megavolt amperes, the apparent power the transformer can deliver. 1 MVA is 1,000 kVA. A transformer is rated in MVA or kVA rather than MW because its heating depends on current and voltage, not on the power factor of the load.

How many amps is a 1 MVA transformer

At 480 V three phase, 1 MVA is about 1,203 A. At 12.47 kV it is about 46 A, and at 13.8 kV about 42 A. The formula is MVA x 1,000,000 divided by (1.732 x volts).

What are standard MVA transformer sizes

Common sizes include 1, 1.5, 2, 2.5, 3, 3.75, 5, 7.5, 10, 12, 15, 20, 25, 30, 40, 50, 60, 75 and 100 MVA, and larger units often carry stacked ratings such as 12/16/20 MVA for their fan stages.

How much does a 100 MVA transformer cost

A published benchmark of $15,000 to $21,000 per MVA gives $1.5 million to $2.1 million for a 100 MVA unit, and highly customized units can reach about $4 million, according to NextMSC. Freight, installation, testing and commissioning are extra.

What is the lead time for a power transformer

Wood Mackenzie's Q2 2025 survey put the average at 128 weeks, and generator step up units at about 143 weeks. Large units are commonly quoted at 30 to 36 months. Surplus and used units can ship much sooner.

What does 12/16/20 MVA mean

It is a stacked rating. The transformer carries 12 MVA self cooled (ONAN), 16 MVA with the first stage of fans and 20 MVA with the second stage (ONAF).