Padmount Supply

Home / Electrical substations

Electrical substations

A substation is a site, not a machine. The transformer is the biggest thing on it and gets the name, but it is one item among a dozen that all have to work together.

Updated November 20, 2026

What a substation does

Three jobs. It transforms voltage between one level of the network and the next, it switches circuits in and out, and it protects everything either side of itself when something faults. A site doing only the second of those is a switchyard rather than a substation.

Distribution substations are the ones most people encounter, stepping transmission voltage down to 12.47 kV, 13.2 kV or 34.5 kV for the feeders. From there the voltage reaches a building through a pad mounted transformer, which is the last step in the chain.

Substation equipment, item by item

EquipmentWhat it does
Power transformerSteps transmission voltage down to distribution voltage. The largest and most expensive item on the site.
Circuit breakersInterrupt fault current under load. Oil, vacuum or SF6 depending on voltage and age.
Disconnect switchesProvide a visible open point for isolation. Not rated to break load current on their own.
Current transformersScale line current down to something a relay or meter can read, usually to 5 A or 1 A.
Potential transformersDo the same for voltage, typically down to 120 V.
Surge arrestersClamp lightning and switching surges to protect the winding insulation.
BusworkRigid tube or strain bus tying the equipment together.
Protective relaysDecide when to trip. Now almost always microprocessor based rather than electromechanical.
Control houseHouses relays, batteries, chargers and communications. Sometimes a prefabricated skid.
Station service transformerSmall unit powering lighting, heaters, chargers and the control house itself.
Grounding gridBuried conductor mat limiting step and touch potential across the yard.
Capacitor banks and reactorsCorrect power factor and manage voltage on long feeders.

Indoor, outdoor and unit substations

Outdoor is the fenced yard on open steel, cheapest per MVA and the default wherever land allows. Indoor puts the equipment in a building or a gas insulated lineup, which costs far more and is used where land is scarce, the environment is severe, or the site has to be hidden.

A unit substation is a different idea. The transformer is bolted directly to switchgear rather than cabled to it, and the whole lineup is assembled and tested as one piece. Single ended has one transformer. Double ended has two with a tie breaker between them, so either side can carry the full load when the other is out. Plants, hospitals and data centres use them for exactly that reason.

Unit substation sizes and full load amps

A unit substation is described by its transformer kVA, its primary voltage and its secondary voltage. Eaton lists secondary unit substations (secondary below 1000 V) with primary voltages from 2.4 to 38 kV, secondary voltages of 208, 240, 480 or 600 V and transformer ratings up to 3750 kVA. Its primary unit substations (secondary 1000 V and above) run from 500 up to 20,000 kVA with primary voltages from 6.9 to 69 kV. Both families come with liquid filled or dry type transformers.

The table gives the full load current on the 480 V secondary for the common secondary unit substation sizes, computed as kVA times 1000 divided by 480 times 1.732. Use it to size the main breaker, the bus and the feeder cables.

Transformer kVAFull load amps at 480 VFull load amps at 208 V
500 kVA601 A1,388 A
750 kVA902 A2,082 A
1,000 kVA1,203 A2,776 A
1,500 kVA1,804 A4,164 A
2,000 kVA2,406 A5,551 A
2,500 kVA3,007 A6,939 A
3,000 kVA3,608 A8,327 A
3,750 kVA4,511 A10,409 A

Dry type suits indoor rooms where a liquid filled unit would need a vault or containment under the electrical code. Liquid filled costs less per kVA at the larger sizes and suits an outdoor pad. See dry type against liquid filled, the substation transformer product line, substation transformers for sale, main power transformers, collector substationsand the 13.8 kV to 480 V transformer page. For how the line is protected, see what a recloser is. To compare the two ends of the grid, see transmission against distribution transformers, switchyard against substation and substation against pad mounted transformers. For 2500 kVA and below on a pad, a pad mounted transformer is often the simpler answer. Switchgear for the secondary side is covered in buying used switchgear and medium voltage switchgear.

Double ended substations

A double ended substation is a unit substation with two transformers. Each one feeds its own secondary bus through a main breaker, and a tie breaker sits between the two buses, normally open. The arrangement is often called main, tie, main. When one transformer or its utility feeder is lost, that main opens and the tie closes, and the surviving transformer picks up both buses.

The consequence is in the sizing. Each transformer has to carry the entire load on its own, so a double ended lineup buys twice the transformer capacity the building normally uses. That redundancy is the point, and it is why hospitals, data centres and process plants specify it where a single ended lineup would leave them dark for the length of a transformer replacement.

Each transformerInstalled in the lineupFull load amps per side at 480 VLoad carried with one side out
1,000 kVA2,000 kVA1,203 A1,000 kVA
1,500 kVA3,000 kVA1,804 A1,500 kVA
2,000 kVA4,000 kVA2,406 A2,000 kVA
2,500 kVA5,000 kVA3,007 A2,500 kVA

How a substation is designed

The sequence is load study, bus arrangement, equipment ratings, protection scheme, grounding grid, then physical layout and clearances. Bus arrangement is the decision that drives cost and reliability together, running from a simple single bus through main and transfer to a ring bus and finally breaker and a half at transmission voltage.

Clearances come from the voltage class and are not negotiable. So does the grounding grid, which is sized from the available fault current and the soil resistivity so that step and touch potentials stay inside safe limits during a fault.

We supply the last step, not the substation. Our line is three phase pad mounted distribution transformers, 45 to 2500 kVA. For substation class equipment the right route is the manufacturer or an EPC, and we would rather say so than take an enquiry we cannot serve properly.

Sources

Eaton, Secondary unit substations design guide and Primary unit substations design guide. Ratings vary by manufacturer and edition, so confirm against the current catalog. Amps are computed.

Related

If the job is a building service rather than a substation, we can price it today. Send the load and the utility voltage or call 786 220 2801.

Not the 60 kVA size, the 60 kVA transformer page explains what 60 MVA draws.

Related, voltage transformer ratios and burdens, pad mounted transformer installation, pad base and clearances and Virginia Transformer plants and products.

The equipment beside the substation, pad mounted switchgear, underground switchgear and switchboards.

Deciding between a fenced substation unit and a locked cabinet unit, substation vs pad mounted transformer.

Same voltage in and out is a switchyard, a changed voltage is a substation, see switchyard vs substation.

CallGet a quote