Home / Products / Solar and battery transformers / BESS step up transformers for battery storage, ratings, specs and lead times
BESS step up transformers for battery storage, ratings, specs and lead times
A BESS transformer steps the power conversion system output, typically 400 to 690 volts, up to the medium voltage collection system of a battery storage plant, and steps it back down when the battery charges. That two way duty is what separates it from a plain distribution unit. We source new, in stock and reconditioned units for storage projects and quote them delivered.
Updated November 15, 2026
Where it sits in a BESS block
NPC Electric describes the chain as battery, inverter or PCS, step up transformer, medium voltage collection and then the grid connection. It gives typical voltage levels of 400 to 690 V at the PCS output, 10 to 35 kV on the medium voltage collection system and 35 to 110 kV at the grid connection. It says large utility scale storage plants often need transformers between 10 MVA and 100 MVA, depending on project size.
The same source says BESS transformers face more dynamic loading than solar transformers because the plant charges and discharges in rapid cycles, and that power electronics make harmonic currents a design factor.
Sizing from the PCS rating
NPC gives a practical reference for matching the transformer to the power conversion system and recommends a margin of 10 to 25 percent above PCS capacity to cover harmonics, overload during frequency regulation and thermal stress during peak shaving.
| Plant type | PCS power | Transformer in the reference |
|---|---|---|
| Small commercial | 1 MW | 1.25 MVA |
| Industrial | 5 MW | 6.3 MVA |
| Utility scale | 10 MW | 12.5 MVA |
| Solar plus storage | 20 MW | 25 MVA |
| Large storage | 50 MW | 63 MVA |
| Utility grid storage | 100 MW | 125 MVA |
These are one manufacturer guide reference ratings, which follow a different rating series than US pad mounted units. Match to your block, not to the table.
Full load amps for common block ratings
Block transformers on US projects are commonly 2.5 to 5 MVA pad mounts. The table is computed from kVA divided by the square root of 3 times the line to line voltage. Dual low voltage winding designs split the current between two windings, so each winding carries about half the figure shown.
| Rating | At 690 V | At 600 V | At 480 V | At 34.5 kV |
|---|---|---|---|---|
| 2,500 kVA | 2,092 A | 2,406 A | 3,007 A | 42 A |
| 3,150 kVA | 2,636 A | 3,031 A | 3,789 A | 53 A |
| 4,000 kVA | 3,347 A | 3,849 A | 4,811 A | 67 A |
| 4,500 kVA | 3,765 A | 4,330 A | 5,413 A | 75 A |
| 5,000 kVA | 4,184 A | 4,811 A | 6,014 A | 84 A |
Computed values rounded to the nearest amp. Use our kVA to amps calculator for other ratings.
What a BESS padmount is built with
Maddox lists what it builds for storage projects, and it reads as a spec checklist.
| Spec point | Maddox BESS padmount listing |
|---|---|
| Rating range | 30 to 10,000 kVA base, up to 35,000 V |
| Duty | Bi directional design, dual voltage |
| Temperature rise | 65 C or 55/65 C |
| Fluid | Mineral oil ONAN or FR3 fluid KNAN |
| Switching and fusing | 600 A LBOR switches, bayonet fuses and current limiting fuses |
| Taps | No load tap changer |
| Options | K factor, E shield, gauges with contacts, Kirk key provisions, viewing and IR windows |
| Dry type, low voltage | 30 to 5000 kVA base, 80/115/150 C rise, bi directional, dual voltage |
Maddox also states a 3 year warranty on new or remanufactured units. Features as listed by one distributor.
Price and lead time
We found no US distributor publishing a BESS padmount price, and we publish none of our own. For public market context, see our power transformer prices page, where the Wood Mackenzie and NextMSC figures sit.
Wood Mackenzie reports average lead times rising from about 50 weeks in 2021 to about 120 weeks in 2024 for transformers overall. Maddox says it keeps thousands of transformers in stock and can have others built with short lead times, and that is the seller own claim, so get a written delivery date for the exact configuration. Because storage blocks repeat the same rating many times, ordering the full count at once usually matters more than the single unit date.
What to send for a quote
- PCS make, model and AC rating in kVA
- PCS side voltage and whether you need a dual low voltage winding
- Collector voltage, for example 34.5 kV
- Rating, impedance, BIL and tap range
- Fluid and fire safety requirements from the site permit
- Auxiliary transformer needs for the block
- Number of units, delivery date and location
Common questions
What is a BESS transformer
It is the step up transformer between the battery inverter or PCS and the medium voltage collection system. It must carry current in both directions as the plant charges and discharges.
What size transformer does a BESS need
Match it to the PCS rating. NPC Electric recommends a margin of 10 to 25 percent above PCS capacity for harmonics and overload.
What voltages do BESS transformers use
NPC Electric gives 400 to 690 V at the PCS, 10 to 35 kV on the collection system and 35 to 110 kV at the grid connection.
How is a BESS transformer different from a solar one
It runs in both directions and faces faster load swings from charge and discharge cycles. Both step up from low voltage to medium voltage.
Can I get a dual low voltage winding
Yes, dual voltage designs are listed by distributors. Say so in the request, with each winding voltage and rating.
Related pages
Sources
- NPC Electric, BESS transformer guide, design, sizing and selection
- Maddox, Transformers for BESS projects
- Wood Mackenzie, Supply shortages and an inflexible market give rise to high power transformer lead times
- NextMSC, US transformer and switchgear prices, lead times and supply constraints 2026, October 2026 update
Market figures are public asking prices and published industry figures, dated where the source gives a date. They are not our prices. A quote from us is a delivered price for a specific unit.