A solar step up transformer takes inverter output at 400 to 690 volts and raises it to a medium voltage collection system, commonly 12.47, 24.94 or 34.5 kV. On a utility scale plant the pad mounted unit at each inverter block is stage one, and a main power transformer in the collector substation is stage two. We quote new, in stock and reconditioned units, delivered, and we publish no prices of our own. The market figures below come from public listings and reports.
Updated November 15, 2026
Where the transformer sits in a solar block
Giga Energy describes the usual utility scale layout as a two stage step up. Pad mounted or collector transformers raise the inverter output to a medium voltage collection system, and a main substation transformer raises it again for transmission. On smaller distributed sites a single pad mounted unit can do the whole job. Giga says the grid side voltage comes from the utility interconnection agreement, so do not freeze the transformer specification before you have it.
Oil immersed units with ONAN or ONAF cooling are the standard at large solar farms, because they handle the daily load cycling well. Dry type units suit indoor or space limited installs at lower capacity. Maddox stocks solar rated low voltage dry type units from 15 to 3000 kVA at 100 to 800 V with K ratings from K1 to K20.
Full load amps by rating and voltage
The table is computed from kVA divided by the square root of 3 times the line to line voltage, so it fits any three phase transformer. The low voltage side is the inverter side and carries the large current, which drives the cable and the busway, so check it before you pick a voltage.
| Rating | At 690 V | At 600 V | At 480 V | At 34.5 kV | At 24.94 kV |
|---|---|---|---|---|---|
| 2,000 kVA | 1,673 A | 1,925 A | 2,406 A | 33 A | 46 A |
| 2,500 kVA | 2,092 A | 2,406 A | 3,007 A | 42 A | 58 A |
| 3,000 kVA | 2,510 A | 2,887 A | 3,608 A | 50 A | 69 A |
| 3,750 kVA | 3,138 A | 3,608 A | 4,511 A | 63 A | 87 A |
| 4,000 kVA | 3,347 A | 3,849 A | 4,811 A | 67 A | 93 A |
| 5,000 kVA | 4,184 A | 4,811 A | 6,014 A | 84 A | 116 A |
Computed values rounded to the nearest amp. For other ratings use our kVA to amps calculator.
Sizing, and the power factor mistake
Giga points to a common error. Many engineers size at 0.8 power factor, a habit from motor loads, but inverters run near unity power factor, so the kW output and the transformer kVA you need are about the same. Giga estimates that applying 0.8 can leave you with a transformer 25 percent larger than the job needs, with more cost, longer lead time and higher losses. Undersizing is worse, since overload brings tripping, heat and faster insulation wear.
Two more points from the same source. Solar output swings with cloud cover and drops to zero at night, so the transformer cycles between load and no load. And if you may add capacity later, size for it now. Our transformer sizing calculator helps with the inverter kVA to transformer kVA step.
Spec points to settle before you order
Maddox lists the options it builds into solar padmounts, and they make a good checklist.
| Spec point | What the listing says |
|---|---|
| Step up duty | Suitable for step up operation, wye wye windings, inverter compatible |
| Harmonics | K rated options for harmonic mitigation, electrostatic shielding |
| Fluid | Mineral oil or biodegradable FR3 fluid |
| Protection and switching | Bayonet and current limiting fuses, LBOR switching, surge arresters |
| Neutral and monitoring | Separated neutral bushings, gauges with alarm contacts, remote monitoring |
| Dry type, low voltage | Five legged core or tertiary winding, electrostatic shielding |
Features as listed by one distributor, not a standard. Confirm each against your utility and inverter requirements.
Listed prices
Giga lists a 2500 kVA three phase padmount at a starting price of $88,000 and a 3750 kVA at a starting price of $114,000. These are the starting prices on its own shop pages, and the configurations shown include 24.94 kV to 480Y/277 V, 12.47 kV to 480Y/277 V and 34.5 kV to 480Y/277 V at 2500 kVA, and 24.94 kV and 13.8 kV primaries at 3750 kVA. Real prices depend on the voltages, impedance, fluid and options. Giga lists free shipping inside the contiguous US on in stock units and a 3 year warranty.
For ratings above this range, see our power transformer price benchmarks, which give a published per MVA range for large units. Our own delivered pricing is not published, because it moves with the factory slot, the freight and the specification.
Lead times
Giga says standard lead times from many manufacturers run from 30 to 52 weeks or longer, and that a pre notice to proceed project should not wait to order. Wood Mackenzie reports that average transformer lead times rose from about 50 weeks in 2021 to about 120 weeks in 2024, and that large substation and generator step up units run 80 to 210 weeks. It adds that as much as 25 percent of global renewable projects could face delay from transformer lead times. Pad mounted units are the faster part of that picture, but a delivery date still needs to be in writing. Our lead time guide breaks it down by type.
What to send for a quote
- Inverter make, model and AC output in kVA
- Inverter side voltage, for example 600 V or 690 V, and whether the winding is wye or delta
- Collector voltage, for example 24.94 or 34.5 kV, from the utility or the collection design
- Rating in kVA, impedance, BIL and tap range
- Fluid, mineral oil or natural ester, and K factor or shield needs
- Number of units and the dates you need them on site
- Delivery location
Common questions
What does a solar step up transformer do
It raises the inverter output, usually 400 to 690 volts, to the medium voltage of the collection system, such as 12.47, 24.94 or 34.5 kV.
What size transformer do I need for a solar inverter
Inverters run near unity power factor, so the transformer kVA is close to the inverter kVA. Giga warns that sizing at 0.8 power factor can oversize the unit by about 25 percent.
How much does a solar pad mount transformer cost
Giga lists a 2500 kVA unit at a starting price of $88,000 and a 3750 kVA unit at a starting price of $114,000. Final prices depend on voltage and options.
How long does a solar transformer take
Giga says standard lead times often run 30 to 52 weeks or longer. Large substation units run far longer.
Do solar transformers need K factor or shielding
Inverters create harmonics that add heat, so K rated designs and electrostatic shielding are common options. Confirm the need with the inverter maker.
Related pages
Sources
- Giga Energy, How to choose the right solar transformer, March 2026
- Giga Energy, 2500 kVA 3 phase padmount transformer
- Giga Energy, 3750 kVA 3 phase padmount transformer
- Maddox, Transformers for solar projects
- Wood Mackenzie, Supply shortages and an inflexible market give rise to high power transformer lead times
Market figures are public asking prices and published industry figures, dated where the source gives a date. They are not our prices. A quote from us is a delivered price for a specific unit.