Home / Comparisons / Switchgear vs Switchboard vs Panelboard, Differences in Ratings, Access and Standards
Switchgear vs Switchboard vs Panelboard, Differences in Ratings, Access and Standards
All three hold breakers on a bus, and the three names get swapped constantly. They are different products with different UL standards, sizes and fault ratings. A panelboard hangs on a wall and is reached from the front. A switchboard is a floor mounted assembly. Switchgear is the heaviest of the three, built with draw out breakers in separate compartments. Load centers are covered too, since a load center is the residential form of a panelboard.
Updated November 16, 2026
| Panelboard | Switchboard | Switchgear | |
|---|---|---|---|
| UL standard | UL 67 | UL 891 | UL 1558 for low voltage metal enclosed switchgear |
| Typical voltage | Up to 600 V, higher ratings exist. Load centers are made for up to 240 V and normally rated to 225 A | Normally up to 600 V | Up to 38 kV |
| Current rating | Up to 1200 A. Load centers normally 225 A, one maker offers up to 600 A | Seldom used under 1200 A, up to 5000 A | Up to 6000 A |
| Mounting | Wall, in a cabinet. Recessed units need 2x6 studs | Floor mounted, usually starting at 18 inches deep | Floor mounted lineup, the largest of the three |
| Breakers | Plug in or bolt on in small sizes, bolt on only in large sizes | Bolt on or draw out | Normally draw out, each in its own compartment |
| Access | Front only, dead front | Front, and often rear and side | Front and rear |
| Short circuit withstand | Rated for 3 cycles | Rated for 3 cycles, higher fault currents than panelboards | Rated for up to 30 cycles |
| Where it sits | Branch circuits and tenant panels | Main service and large feeders | Critical and industrial mains, outdoor service gear |
| Factory lead time, one 2026 Arizona fabricator | 3 to 7 weeks, same week from stock | 10 to 18 weeks for 800 to 2000 A | 16 to 26 weeks, 20 to 36 weeks for 5 kV class |
Which you actually need
Pick by amperage and fault current first. Under about 1200 A and a modest available fault current, a panelboard is almost always the right and cheapest answer. Between 1200 A and 5000 A at 600 V or less, a switchboard is the normal main service. Choose switchgear when the system needs draw out breakers so a breaker can be serviced without shutting down the main, when fault current is high, or when the voltage is above 600 V. In all three cases the secondary of the pad mounted transformer lands on one of these, so size the transformer and the gear together, and check the gear short circuit rating against the transformer kVA and impedance.
Panelboards, switchboards and switchgear are all defined in Article 100 of the NEC. The Code does not limit any of them to a voltage or current range. The ranges above are what manufacturers such as ABB, Eaton and Schneider Electric actually build, so a specific product can fall outside them.
Main service gear is often mounted outside the building. A section of the gear can hold the utility current transformers and meter, so no separate CT enclosure is needed. Panelboards are then used downstream wherever possible to save wall and floor space.
Medium voltage switchgear above 1000 V follows different standards than the low voltage gear in the table. Read our guide on what switchgear is for the voltage classes, metal clad and metal enclosed construction, and arc resistant designs.
Sources
- IAEI Magazine, Basics of Switchboards, Switchgear and Panelboards
- Tech Energy America, switchgear vs panelboard, standards and 2026 lead times
- Delta Wye Electric, switchgear vs switchboard
Working from a specification that uses one of these terms loosely? Send it over and we will tell you which equipment it is actually calling for, before you order the wrong thing. Get a quote or call 786 220 2801.