Generator Load Bank Testing and What a Load Bank Does
A load bank is a device that turns electrical power into heat so a generator can be run at a known load without the building. It is used to prove a standby generator can carry its rated load, to burn off the unburned fuel that builds up when an engine runs lightly and to commission a new set. NFPA 110 asks for a monthly exercise at 30 percent of nameplate or the maker minimum exhaust temperature. A load bank is how an owner reaches that when the building load is too small.
Updated November 17, 2026
What a load bank is
A load bank is a bank of resistors, and sometimes inductors, with a cooling fan, a breaker and controls, that connects to a generator and draws a set amount of power. Building load is unpredictable and usually far below the generator rating. A load bank gives a controlled number, such as 500 kW, so the test shows what the engine, alternator, cooling and controls do at that load. Permanent units sit on a pad outside the generator building and portable units come on a trailer.
Resistive and reactive load banks
A resistive load bank draws only real power, so it loads the engine in kW at a power factor of 1.0. A resistive and reactive bank adds inductors so it can draw at 0.8 power factor, which is the rating of most standby sets. That loads the alternator to its full kVA as well as the engine to its kW. A resistive bank is enough to exercise the engine. The combined type is used when the alternator and voltage regulator also need to be proven at rated current.
When NFPA 110 calls for a load test
Emergency and standby generators under NFPA 110 are exercised monthly. A diesel set runs at least 30 minutes, at 30 percent or more of nameplate kW or at the minimum exhaust gas temperature the maker gives. If monthly runs do not reach that load, an annual supplemental load bank test is needed. In the older schedule that test is two continuous hours, 25 percent for 30 minutes, 50 percent for 30 minutes and 75 percent for 60 minutes. Newer summaries list 50 percent for 30 minutes followed by 75 percent for 60 minutes, 1.5 hours in total. The edition your authority adopted decides which applies. A Level 1 system also needs a longer test every 36 months. Sources describe it differently, as 30 percent of nameplate for 4 hours in one article and as three hours at 30 percent or the exhaust temperature then one hour at 75 percent in another. Check the text of the edition in force. Health care facilities also fall under NFPA 99, which asks for at least 30 minutes under load at intervals of no more than 30 days.
Load steps in kW
The table converts the percent steps to kW for four common sizes. The 25, 50 and 75 percent steps are the older two hour schedule. The 30 percent column is the monthly minimum load. Every value is the generator nameplate kW times the percent.
| Generator | 25% of nameplate kW | 30% of nameplate kW | 50% of nameplate kW | 75% of nameplate kW | 100% of nameplate kW |
|---|---|---|---|---|---|
| 100 kW | 25 | 30 | 50 | 75 | 100 |
| 250 kW | 62 | 75 | 125 | 188 | 250 |
| 500 kW | 125 | 150 | 250 | 375 | 500 |
| 1,000 kW | 250 | 300 | 500 | 750 | 1,000 |
Percentages are of nameplate kW, not kVA. A 625 kVA set at 0.8 power factor is a 500 kW set and its 75 percent step is 375 kW.
Step by step test procedure
One published procedure, from a member of the NFPA 110 technical committee, runs as follows. Start the generator and run it until the water temperature stabilizes. Transfer all manual or automatic transfer switches to the emergency source. Step load the generator with the load bank until the target load is reached. At the end, remove the load bank load first, then transfer all switches back to normal and let the generator cool down as the maker directs. Adding the building load first means the building is already on emergency power if the utility fails during the test. Lockout and tagout and the PPE required by NFPA 70E apply, since the bus is live.
How to connect the load bank
The same article says the load bank should be paralleled with the building load, so no reconnection is needed. It connects to a dedicated bus downstream of an overcurrent device in a switchboard, or to a bus in a NEMA 3R connection box outside the generator building. A permanent pad mounted load bank wired into the switchboard can be tripped off automatically if the utility fails. Facilities that cannot lose power also keep a connection point so a portable generator can be backfed if the permanent one fails during the test.
Sizing a load bank
Pick a load bank at least as large as the load you need to put on the generator, which for the 75 percent step is 0.75 times the nameplate kW. For a 500 kW set that is 375 kW of load bank, or 500 kW if you also want to test at full rating. If the building already carries part of the load the bank only has to make up the difference. Use a resistive and reactive bank at 0.8 power factor when the alternator is part of the test. Voltage, three phase and the connection point have to match the generator.
What a load test shows
Running under load shows engine temperatures, oil pressure, voltage and frequency regulation, fuel system performance and cooling. It also burns off the unburned fuel and carbon that lightly loaded diesels build up, known as wet stacking. Test records are part of the maintenance file for health care and many commercial buildings.
Cost
Costs for load bank rental and testing are quoted by service companies and depend on the size, the distance and the time. No dependable public price list was found for this page, so none is shown. Ask for quotes that include transport, connection, the test duration and a written report.
Related pages
Common questions
What is a load bank
A load bank is a device with resistors, and sometimes inductors, that draws a set amount of electric power and turns it to heat, so a generator can be tested at a known load.
How often must a generator be load tested
NFPA 110 asks for a monthly run of at least 30 minutes at 30 percent or more of nameplate kW, or the maker minimum exhaust temperature. If the monthly runs fall short, an annual load bank test is needed, and a Level 1 system has a longer test every 36 months.
What are the load steps in an annual load bank test
The older schedule is 25 percent for 30 minutes, 50 percent for 30 minutes and 75 percent for 60 minutes, two hours in all. Newer summaries give 50 percent for 30 minutes then 75 percent for 60 minutes. Follow the edition your inspector uses.
Is a resistive or a reactive load bank better
A resistive bank loads the engine in kW. A resistive and reactive bank at 0.8 power factor also loads the alternator to its full kVA. Most standby sets are rated at 0.8, so the combined type tests the whole set.
What size load bank do I need
At least the load of the highest step. For a 75 percent step on a 500 kW generator, 375 kW. If the building supplies part of the load, the bank covers the rest.
Can building load be used instead of a load bank
Yes, where the building can put enough load on the generator, and it lowers the utility bill during the test. The cost is the fuel burned. Moving non essential load onto the generator is often not practical, which is why permanent pad mounted load banks are used.
Sources
- EC&M, Testing Generators with a Portable Load Bank
- Avtron Power, using load banks to meet emergency power generating system codes and standards
- Sunbelt Solomon, NFPA 110 compliance guide to generator load bank testing
- Trystar, benefits of load bank testing
Free to cite with a link to this page. Work out current at any rating with the kVA to amps calculator.