Substation transformers for sale, new, reconditioned and surplus, 5 to 100 MVA

A substation transformer steps transmission or subtransmission voltage down to distribution voltage, for example 138 kV or 69 kV to 34.5 kV or 13.8 kV. Ratings run from a few MVA to 100 MVA and beyond, and the nameplate carries up to three MVA ratings for different cooling stages. New units are on very long lead times, so most buyers compare new, reconditioned and new surplus units that were never energized. We quote all three, delivered.

Updated November 15, 2026

What counts as a substation transformer

A substation transformer is an oil filled power transformer, usually three phase, that sits in a utility, industrial or generation substation and feeds the distribution system. It is larger than a pad mounted unit. Our own pad mounted pages cover units to about 2500 kVA, and this page covers the range above that.

One manufacturer brochure for secondary substation units lists voltages up to 34.5 kV and ratings up to 15 MVA ONAN. Utility bids go much higher. One public bid lists a 138 kV primary unit rated 15, 20, 25 and 28 MVA with a 7.557 and 13.09 kV secondary, which is a common utility distribution substation size.

Ratings and cooling classes

A substation transformer carries one rating per cooling stage. ONAN means oil natural, air natural, with no fans or pumps. ONAF adds fans. A nameplate such as ONAN, ONAF, ONAF lists three MVA values, base, first fan stage and second fan stage. IEEE C57.12.00 based design notes give 65 C average winding rise as the common basis, with an 80 C hot spot rise, and ONAN, ONAF, ONAF as the standard cooling arrangement.

Two examples from public sources show how the stages stack. A bid for a 12.0, 16.0 and 20.0 MVA unit at 65 C rise lists ONAN, ONAF, ONAF cooling, and the same bid lists 10.71, 14.29 and 17.86 MVA at 55 C rise. A surplus listing for a 15, 20 and 25 MVA unit, 69 kV to 34.5 kV, lists a 65 C rise, an ABB load tap changer and 350 kV BIL. The fan multipliers differ by standard and by source, so confirm them against the governing specification before you compare units.

Rating exampleCooling stagesRise basisSource type
12 and 16 and 20 MVAONAN, ONAF, ONAF65 CPublic utility bid
10.71 and 14.29 and 17.86 MVAONAN, ONAF, ONAF55 CSame public bid
15 and 20 and 25 and 28 MVA, 138 kV to 7.557 and 13.09 kVONAN, ONAF, ONAF55 and 65 CSecond public utility bid
15 and 20 and 25 MVA, 69 kV to 34.5 kVONAN, ONAF, ONAF65 CSurplus listing, unused, 2023

These are examples from the sources we read, not a standard rating chart. Use the nameplate or the specification for the units you are matching.

Full load amps by MVA and voltage

Full load current sets the size of the breakers, bus and cable on each side. The table is computed from MVA divided by the square root of 3 times the line to line voltage, so it applies to any three phase transformer. Use the highest MVA stage on the nameplate for the worst case current.

MVAAt 138 kVAt 69 kVAt 34.5 kVAt 13.8 kV
5 MVA21 A42 A84 A209 A
10 MVA42 A84 A167 A418 A
12 MVA50 A100 A201 A502 A
20 MVA84 A167 A335 A837 A
25 MVA105 A209 A418 A1,046 A
30 MVA126 A251 A502 A1,255 A
50 MVA209 A418 A837 A2,092 A
100 MVA418 A837 A1,673 A4,184 A

Computed values rounded to the nearest amp. For other sizes use our kVA to amps calculator.

Lead times, new against reconditioned

Wood Mackenzie's survey for the second quarter of 2025 put the average power transformer lead time at 128 weeks and generator step up units at 144 weeks, against about 30 weeks for distribution transformers. A Rystad Energy report puts lead times above 12 months for units over 20 MVA and above 24 months for units of 100 MVA and up in Europe and North America. Rystad also expects the peak to ease. A May 2026 report still gave the average at 128 weeks.

Resellers and remanufacturers claim much shorter times, and these are vendor claims for their own inventory. Maddox says new US built transformers run 60 to 80 weeks and its remanufactured units stand at 1 to 4 weeks. JCL Energy says reconditioned units typically deliver within 40 weeks. Giga Energy says it can offer 26 weeks on custom substation units. Treat each as the seller's own figure and get the date in writing.

PathPublished timeWho says so
New, average power transformer128 weeksWood Mackenzie, Q2 2025
New, generator step up144 weeksWood Mackenzie, Q2 2025
New, over 20 MVAAbove 12 monthsRystad Energy
New, 100 MVA and upAbove 24 monthsRystad Energy
New, custom substation unitAs fast as 26 weeksGiga Energy, vendor claim
ReconditionedWithin 40 weeksJCL Energy, vendor claim
Remanufactured, in stock1 to 4 weeksMaddox, vendor claim

Lead times move and differ by size and voltage. They are not our quote.

Buying paths compared

New from a factory gives the exact specification and a full warranty, with the longest wait. Reconditioned means a used unit that has been inspected, tested and repaired, often with new gaskets, oil processing and bushings. New surplus means a unit built for a project that was never energized, which gives a new nameplate with stock timing, but only in the ratings that exist. Surplus Record lists a 2023 unused 15, 20 and 25 MVA unit from CTG Power Systems with the price on request and with transport, rigging, setting, field testing and commissioning excluded.

Buyers who need a date more than a custom design usually start with what already exists. Match MVA, both voltages, impedance and the tap changer first. Then compare vector group, BIL, cooling and the oil test results. See our guide to used and surplus transformers for the test list and for warranty norms.

Price

Substation transformers are quoted per project. The listings we read for large units show the price on request, and we publish no prices of our own. For public market ranges and the sources behind them, see our power transformer prices page. Delivered pricing depends on the rating, the voltage class, the condition and the freight, because a unit of this size ships as a heavy haul with rigging at both ends.

Rental and mobile units

If the date matters more than owning the unit, rental or a mobile substation can bridge the wait. See our transformer rental page and our guide to mobile substations and temporary power.

What to send for a quote

  • MVA rating for each cooling stage, for example 12, 16 and 20 MVA ONAN, ONAF, ONAF
  • Primary and secondary voltage, with taps, for example 69 kV to 13.8 kV
  • Impedance, vector group and BIL
  • Load tap changer or de energized tap changer, and the regulation range
  • Cooling class, rise basis and fluid, mineral oil or natural ester
  • Sound level limit and any site or utility specification
  • New, reconditioned or surplus, and the warranty you need
  • Delivery location and the date you need it on site

Common questions

What is a substation transformer

It is an oil filled power transformer in a substation that steps transmission or subtransmission voltage down to distribution voltage. Examples in public bids include 138 kV to 13.09 kV and 69 kV to 34.5 kV, at 12 to 28 MVA.

What do ONAN and ONAF mean

ONAN is oil natural, air natural, with no fans. ONAF adds fans for more rating. A nameplate that reads ONAN, ONAF, ONAF lists three MVA values, one per cooling stage.

How long does a substation transformer take

Wood Mackenzie put the average power transformer at 128 weeks in the second quarter of 2025. Resellers claim shorter times for reconditioned and stock units, and those are vendor claims.

Can I buy a used or surplus substation transformer

Yes. Reconditioned and never energized surplus units are sold, in the ratings that exist. Match MVA, both voltages, impedance and tap changer, and ask for the test report.

What is the full load current of a 20 MVA transformer

At 69 kV it is about 167 A and at 13.8 kV about 837 A. The formula is MVA divided by the square root of 3 times the line to line kV.