UPS sizing calculator

A 200 kW critical load with 25 percent growth at 0.9 power factor and 80 percent maximum loading needs about 347 kVA of UPS, so a 400 kVA unit. Enter your load, margins and runtime to get UPS kVA, the next standard size and battery energy.

Updated November 18, 2026

Design load with growth250.0 kW
UPS kVA needed347.2 kVA
Next standard UPS size400 kVA
UPS kW rating at that size360 kW at 0.9 PF
Battery energy for 10 minutes55.6 kWh

UPS standard sizes here are common catalog steps, not one maker's line. Confirm the kW rating on the data sheet of the unit you buy, because many UPS are rated at unity power factor and others at 0.9.

The formulas

Design load in kW equals critical load times one plus the growth margin. UPS kVA equals design load divided by the output power factor and by the maximum loading. Battery kWh equals design load times runtime in hours, divided by efficiency, times one plus the aging margin.

UPS size chart for common loads

This chart uses 25 percent growth, 0.9 power factor, 80 percent maximum loading, a 10 minute runtime, 90 percent efficiency and a 20 percent aging margin. Those are planning assumptions.

Critical load kWDesign kWUPS kVA neededNext standard sizeBattery kWh for 10 minutes
1012.517.420 kVA2.8
2025.034.740 kVA5.6
5062.586.8100 kVA13.9
100125.0173.6200 kVA27.8
200250.0347.2400 kVA55.6
500625.0868.11,000 kVA138.9
1,0001,250.01,736.12,000 kVA277.8

Worked example for 600 kW

Take 600 kW critical load. Growth of 25 percent gives 750 kW. Dividing by 0.9 power factor and 0.8 maximum loading gives about 1,042 kVA. The next standard size in the table is 1200 kVA. With N plus 1 redundancy you would add one more module of the same size.

What sits upstream

A UPS is fed by a utility transformer or a generator, and large units charge batteries on top of carrying the load. Size those for the UPS input kVA. See UPS kVA ratings, the kVA to amps calculator for feeders, static transfer switches and generators. For the whole data center chain see data center transformers and the PUE calculator.

Specifying power for a data hall, request a quote with the kW, voltage and redundancy.

Put this calculator on your site

Free for contractors, electricians, schools and trade sites. Paste this code into any page.

Common questions

How do I size a UPS

Add up the critical load in kW, add a growth margin, divide by the UPS power factor, and keep the UPS under a loading ceiling so it has room for inrush and surges. Then pick the next standard size up. Battery size comes from the runtime you need.

What is the difference between UPS kVA and kW

kVA is the apparent power the UPS can deliver and kW is the real power. kW equals kVA times the output power factor. A UPS rated at 100 kVA and 0.9 power factor delivers 90 kW, and one rated at unity power factor delivers 100 kW. Read the data sheet, because both ratings are common.

How big a UPS does a 200 kW load need

With 25 percent growth, a 0.9 power factor and a limit of 80 percent loading, a 200 kW load needs about 347 kVA, so the next standard size is 400 kVA. This page uses the figures you can change in the calculator, they are planning assumptions and not a rule.

How do I size the battery for a UPS

Battery energy equals load in kW times runtime in hours, divided by the efficiency of the battery and inverter, plus a margin for aging. A common planning allowance for aging is 10 to 20 percent, from the sources listed below. Always confirm the runtime against the battery maker discharge tables.

How much growth margin should I add

Sources suggest 20 percent for a three to five year horizon and 20 to 30 percent for growth, inrush and metering error. Rapidly growing sites use 40 to 50 percent. The right figure is the one your load forecast supports.

Do I need a transformer for a large UPS

Large UPS often take a three phase feed from a transformer, and many sites add an output or isolation transformer. Size the upstream transformer and generator for the UPS input kVA, which is above the output kVA because of battery charging, then check with the maker.

Sources

  • Legrand Data Center, why proper UPS sizing is crucial for data center applications, and understanding UPS capacity, kVA equals kW divided by power factor.
  • GSE blog on UPS sizing for server rooms and data centers, growth margin of 20 percent standard for three to five years and 40 to 50 percent for aggressive plans.
  • Electrical Trader, data center UPS sizing planning steps, 20 to 30 percent for growth, inrush and metering error.
  • Engineering calculators, UPS sizing calculator for data centers, worked example of 750 kW design load at 0.9 power factor and 80 percent derate giving about 1,042 kVA, and a battery runtime formula using efficiency of 85 to 95 percent for VRLA with a 10 to 20 percent aging margin. Treat the IEEE 485 attribution on that page as unconfirmed.
  • All kVA and kWh numbers here are computed from your inputs, not read from a UPS data sheet. Standard size steps are common catalog sizes, not one maker.
CallGet a quote