Home / Guides / Data Center Transformers, Types, Sizes and Lead Times
Data Center Transformers, Types, Sizes and Lead Times
A data center uses several layers of transformers. A utility or customer owned substation transformer brings in the power, pad mounted or unit substation transformers step it down to 480 volts for the halls, and smaller dry type units feed power distribution units. Lead time is the main buying problem. Contractor reports for 2026 projects put pad mounted units at 40 to 65 weeks.
Updated November 18, 2026
Where transformers sit in a data center
Power arrives at medium or high voltage from the utility. A substation transformer reduces it to distribution voltage, pad mounted or unit substation transformers then drop it to a low voltage such as 480Y/277, and the UPS, switchgear and power distribution units carry it to the racks. Every step is a place where a transformer can be specified, and every one counts as overhead in PUE.
Types in use
The common pad mounted transformer is a three phase, liquid filled unit with a sealed tank, set outdoors on a concrete pad. Unit substations combine a transformer with switchgear in one lineup. Dry type units are used indoors where oil is not wanted, typically at the power distribution level. Which one fits depends on the site, the yard space and the fire rules of the project.
Common sizes and full load current
Sizes of 1,500 to 3,750 kVA are typical for pad mounted units feeding a data hall block. Match the transformer to the UPS input kVA and the redundancy design, since the chain is sized for the load plus losses, not the IT load alone. Use the UPS sizing calculator to find the input side, and the transformer sizing calculator to pick a standard size.
Lead times in 2026
Terrapin Construction Group reported 40 to 65 weeks for pad mounted distribution transformers on its active 2026 projects, and another contractor guide puts three phase pad mounted units for data centers at 40 plus weeks. Wood Mackenzie expected the three phase pad mounted shortage to worsen. These are class level figures, not quotes for one size.
Cost and price trend
Trade reports say pad mounted prices rose 12 to 18 percent versus 2023, and a Wood Mackenzie index summary showed pad mounted three phase prices up about 20 percent in the second quarter of 2025. Other reports project further increases of about 4 to 10 percent over the next year, depending on type. We publish no list prices. A real number needs a quote for the kVA, voltage, impedance and efficiency you specify.
How to buy faster
Lock the kVA, voltage, impedance and tap range early, since late changes restart the factory slot. Ask for stock and reconditioned units in parallel to a new order, and consider standard sizes over odd ones. Used and refurbished units can bridge a schedule gap on a temporary phase of a campus.
Efficiency and PUE
Transformer losses are small next to cooling, but they run at all hours and they are heat that cooling must remove. Specify efficiency in the quote and compare no load and load losses. See the PUE calculator for what each 0.1 of PUE costs a year.
Related pages
Full load current of common data center transformers
Current at 480Y/277 volts on the secondary and at 12,470 volts on the primary, computed as kVA times 1,000 divided by volts times the square root of three.
| kVA | MVA | Amps at 480 V | Amps at 12,470 V |
|---|---|---|---|
| 1,500 | 1.5 | 1,804 | 69.4 |
| 2,000 | 2 | 2,406 | 92.6 |
| 2,500 | 2.5 | 3,007 | 116 |
| 3,000 | 3 | 3,608 | 139 |
| 3,750 | 3.75 | 4,511 | 174 |
Common questions
Do data centers use transformers
Yes, at several levels. A utility or site substation transformer takes in the power, pad mounted or unit substation transformers step it down to 480 volts, and smaller transformers feed power distribution units.
What size transformer does a data center need
It depends on the load, the UPS input and the redundancy. Pad mounted units from 1,500 to 3,750 kVA are common building blocks. Compute current with the table above and pick a standard size with the transformer sizing calculator.
How long is the lead time for a data center transformer
Contractor reports for 2026 projects give 40 to 65 weeks for pad mounted distribution transformers and 40 plus weeks for three phase units.
How much does a data center transformer cost
No list price is given here. Trade reports show pad mounted prices up 12 to 18 percent versus 2023, and a Wood Mackenzie index showing about 20 percent for three phase pad mounted units. Request a quote with your kVA and voltage.
What is the difference between a pad mounted and a dry type transformer for a data center
A pad mounted unit is liquid filled and sits outdoors on a pad. A dry type transformer has no liquid and is used indoors. Many sites use both, pad mounted at the yard and dry type inside the building.
Sources
- Gigaenergy, lead time delays for data centers
- POWER Magazine, transformers in 2026
- POWER Magazine, making the connection executive summary
- Electrical Trader, energy efficient transformers price trends 2026
- Kitco, US power transformer buyers scramble for imports and factory slots
Free to cite with a link to this page. Work out current at any rating with the kVA to amps calculator.