Switchgear lead times
Low voltage switchgear and switchboards run roughly 16 to 54 weeks in published 2026 figures, and medium voltage gear runs far longer. The ranges below come from industry sources, not our quotes. We quote real lead times for the specific unit, including reconditioned stock that ships faster.
Updated November 17, 2026
Published ranges
These figures come from trackers, articles and dealer listings read in November 2026. They are directional and differ by maker and configuration.
| Gear | Published lead time | Source type |
|---|---|---|
| General low voltage switchgear | about 24 weeks | ElectroIQ tracker cited by DataM Intelligence |
| Siemens apparatus low voltage switchgear | about 54 weeks | ElectroIQ tracker cited by DataM Intelligence |
| Custom 480 V and 600 V lineups from major makers | 16 to 26 weeks, up from 12 weeks before 2022 | Industry article, May 2026 |
| Standard switchgear | roughly 20 to 44 weeks | 2026 lead time guide |
| Medium voltage switchgear | about 130 weeks average | ElectroIQ tracker cited by DataM Intelligence |
| 15 kV metal clad gear | 52 to 80 weeks | Terrapin data, June 2026 |
| Siemens switchboards, dealer quick ship | 6 to 8 weeks, custom 10 to 12 weeks | Dealer listing, a seller claim |
Custom switchboard and panel configurations carry the longest lead times in the sources read. The dealer figure is not an independent measurement.
Ways to shorten the wait
Quick ship programs use pre configured designs. Vertiv runs one for 4000 A switchboards and says it cuts lead time against engineered to order builds. Choosing a standard bus size, standard enclosure and common breaker frames keeps a unit out of the custom queue.
Reconditioned and new surplus gear is the other route. It can ship in weeks and matches old lineups exactly. Our used switchgear page lists test and warranty norms.
What drives the wait
Breaker and bus parts, factory slots, custom enclosures and approval drawings all add weeks. Data center demand has stretched lead times at the large makers, and orders placed early in a project fare better.
Transformer lead times
Switchgear is often ordered with a transformer. See our transformer lead time guide for the matching figures.
What to send for a quote
- Gear type and voltage class
- Bus amps and short circuit rating
- Number of sections or breakers
- Date needed on site
- Whether reconditioned or surplus gear is acceptable
- Delivery ZIP code
Common questions
How long does low voltage switchgear take
Published 2026 figures range from about 16 to 26 weeks for custom 480 V lineups up to about 54 weeks for Siemens apparatus gear in one tracker.
How long does medium voltage switchgear take
One tracker averages about 130 weeks, and Terrapin data gives 52 to 80 weeks for 15 kV gear.
Is reconditioned switchgear faster
Usually yes, since the unit already exists. Availability depends on the exact make, rating and voltage.
Can you give a firm lead time
We quote the lead time for the specific unit and supplier, and it can change with the factory queue.
Related pages
Sources
- DataM Intelligence, the electrical gear bottleneck
- Electrical panel lead times in 2026, what contractors and facilities managers need to know
- IndustrialSage, switchgear lead times 2026
- Surplus Record, new Siemens switchboards quick ship listing
- Vertiv, Powerboard UL 891 switchboard quick ship program
- Terrapin lead time data, as cited on our metal clad switchgear page
Market figures are public asking prices and published industry figures, dated where the source gives a date. They are not our prices. A quote from us is a delivered price for a specific unit.