Temporary Power Pole Requirements, Cost and How to Get One

A temporary power pole is a treated post at a construction site that carries a meter socket, a service disconnect and a panel with receptacles, so builders have power before the permanent service is ready. The utility sets the rules for the pole and connects it to the line. The electrical contractor builds it and the inspector approves it. Requirements differ by utility, so this guide gives what several utility specifications ask for, the NEC rules that apply and the published cost figures, and says plainly where sources disagree.

Updated November 17, 2026

What a temporary power pole is and who supplies what

The pole is customer owned equipment, and the electrician builds it to the utility specification. The utility supplies the line or transformer and the meter and connects the service after inspection. A 100 amp or 200 amp single phase 240 volt service is the usual size. Larger sites with cranes or welders use a pad mounted transformer or a mobile unit, see mobile substations and temporary power and transformer rental.

What utility specifications ask for

Specifications vary, and the ones below are examples from cooperatives and a public power utility. They agree on the pole, the ground rod and the wire size and disagree on setting depth. Always get the current specification from your own utility, because the pole class, the depth and the approved meter sockets are theirs to set.

ItemWhat the specs saySource
PoleA 4 by 4 treated pole with bracesA cooperative spec found by search
Setting depthAbout 3 feetMygea and Fannin Electric Cooperative
Setting depth and height4 feet in the ground, at least 12 feet above grade, taller if NEC clearances need itOmaha Public Power District meter manual
Ground rod5/8 inch rod, 8 feet long, with 6 AWG copperFirst Electric Cooperative and Hilco
Ground electrodeThe customer furnishes the electrode and clampHilco
Wire, 100 amp4 AWG copperA utility spec sheet found by search
Wire, 200 amp2/0 copper, with 2 inch conduitFannin Electric Cooperative and Nueces Electric
ProtectionGFCI protection on the temporary panelFannin Electric Cooperative
Moving the poleInspected again each time it is movedMygea

Size of the service

A 100 amp service at 240 volts is 24 kVA and a 200 amp service is 48 kVA, computed as amps times volts divided by 1,000. One utility spec sheet lists 4 AWG copper for 100 amps and Fannin lists 2/0 copper for 200 amps, which is the same dwelling wire size the 83 percent rule in NEC 310.12 gives. The service wire size chart has the whole table, and the electrical service size chart shows the kVA at 80 percent loading.

NEC Article 590 rules

Article 590 covers temporary wiring. Temporary power and lighting are allowed during the construction, remodeling, maintenance, repair or demolition of buildings, structures or equipment (590.3(A)). Temporary wiring must be removed immediately when the work it served is done (590.3(D)). Decorative lighting can stay up to 90 days (590.3(B)). All other NEC requirements still apply unless Article 590 changes them (590.2(A)), and wiring methods must be acceptable to the authority having jurisdiction (590.2(B)), per EC&M. Ground fault protection is required on temporary construction receptacles, and a rule change in the 2008 NEC made clear that it covers power from on site generators as well as from the utility. Check the edition your jurisdiction has adopted.

Materials list

The parts below are what the utility specifications above call for. Quantities and approved parts come from your utility and your electrician.

PartNotes
Treated pole with bracesSize and class per the utility, set at the depth above
Meter socketApproved by the utility, rated for 100 or 200 amps
Service conductors4 AWG copper for 100 amps, 2/0 copper for 200 amps, in conduit
Service disconnect and panelMain breaker and branch breakers sized to the site tools
GFCI protection and receptaclesOn the temporary panel or at each 120 volt receptacle
Ground rod and ground wire5/8 inch by 8 foot rod with 6 AWG copper in most cooperative specs
Weatherhead and fittingsFor an overhead service drop

Cost

Published estimates disagree. Fixr, updated January 2025, gives a national average of $2,000 for temporary power on a construction site with a typical range of $1,000 to $4,000, and $1,700 to $4,500 to install a temporary power system. LatestCost puts a 200 amp single phase pole at $4,000 low, $9,000 average and $15,000 high, with permit fees from $200 to $1,500. Engineerfix says a 200 amp panel and meter socket cost about $100 to $200 more than the 100 amp versions. A forum post, not a survey, reports $275 for a 100 amp temporary service installed with two ground rods. The spread comes from distance to the line, permit fees and utility connection charges, which sit outside the electrician quote. Get a bid from a local electrician and ask the utility for its fee schedule.

SourceFigureScope
Fixr, January 2025$2,000 average, $1,000 to $4,000 rangeTemporary power for a construction site
Fixr, January 2025$1,700 to $4,500Install a temporary power system
LatestCost$4,000 low, $9,000 average, $15,000 high200 amp single phase pole
LatestCost$200 to $1,500Permit fees
Engineerfix$100 to $200 more200 amp panel and meter socket against 100 amp

Steps to get power on

Ask the utility for its temporary service specification and fee schedule. Pull the electrical permit. Have the electrician build the pole, the panel and the ground to the specification. Schedule the inspection, and the utility connects the service once the inspector approves it. When the permanent service is ready, remove the pole as 590.3(D) requires, and see the pad mounted transformer installation guide for the permanent side.

Related pages

Common questions

How deep does a temporary power pole need to be

Utility specifications differ. Mygea and Fannin Electric Cooperative give about 3 feet, and the Omaha Public Power District manual calls for 4 feet with at least 12 feet above grade. Use the depth your utility gives.

How much does a temporary power pole cost

Published figures range widely. Fixr gives $1,000 to $4,000 for temporary construction power with an average of $2,000. LatestCost gives $4,000 to $15,000 for a 200 amp pole with a $9,000 average, plus $200 to $1,500 in permits.

What size wire for a 200 amp temporary power pole

Two cooperative specifications call for 2/0 copper for a 200 amp temporary service, and one adds 2 inch conduit. For a 100 amp service one utility spec sheet lists 4 AWG copper.

How do you ground a temporary power pole

Cooperative specifications call for a 5/8 inch ground rod, 8 feet long, with 6 AWG copper ground wire. One utility has the customer furnish the electrode and clamp. Your utility and inspector set the final detail.

Does a temporary power pole need GFCI

Yes. NEC Article 590 requires ground fault protection on temporary receptacles used for construction, and Fannin Electric Cooperative requires GFCI protection on the temporary panel.

How long can a temporary service stay

NEC 590.3 allows temporary power during construction, remodeling, maintenance, repair or demolition and requires removal immediately when the work is done. Decorative lighting is limited to 90 days. Your utility may set its own limit.

Who installs a temporary power pole

A licensed electrician builds it to the utility specification and the inspector approves it. The utility connects the service and sets the meter.

Sources

Free to cite with a link to this page. Work out current at any rating with the kVA to amps calculator.