Padmount Supply

Home / Charts / Electrical service size chart, how many kW is a 200 amp service

Electrical service size chart, how many kW is a 200 amp service

A 200 amp, 240 volt single phase service can deliver 48 kVA, which is 48 kW at unity power factor. That is amps times volts divided by 1000. A 100 amp service is 24 kVA, a 400 amp service is 96 kVA, and the same 200 amps on a 480 volt three phase service is 166 kVA. The tables below work out every common service size so you can read kW or kVA straight off the row.

Updated November 16, 2026

Single phase 120/240 volt service, 60 to 600 amps

Kilovolt amps equal amps times 240 divided by 1000 for the two hot legs of a 120/240 volt service. The 80 percent column shows the figure if you hold the load to 80 percent of the service rating, a common design margin for loads that run for hours. Each hot leg alone is 120 volts, so a single 120 volt leg carries half of the full kVA.

Service ampskVA at 240 VkVA at 80 percentkVA on one 120 V leg
6014.411.57.2
10024.019.212.0
12530.024.015.0
15036.028.818.0
20048.038.424.0
22554.043.227.0
30072.057.636.0
40096.076.848.0
600144.0115.272.0

Computed, kVA = amps x volts / 1000. kW equals kVA times power factor, so kW and kVA match only at a power factor of 1.0.

Three phase service, 125 to 1200 amps

Three phase kVA equals amps times line to line volts times the square root of 3 divided by 1000. The 480 volt column also shows the 80 percent figure.

Service ampskVA at 208 VkVA at 240 VkVA at 480 V480 V at 80 percent
12545.052.0103.983.1
15054.062.4124.799.8
20072.183.1166.3133.0
22581.193.5187.1149.6
300108.1124.7249.4199.5
400144.1166.3332.6266.0
600216.2249.4498.8399.1
800288.2332.6665.1532.1
1000360.3415.7831.4665.1
1200432.3498.8997.7798.1

Computed, kVA = amps x volts x 1.732 / 1000.

kW versus kVA

A service is rated in amps, and amps times volts gives kVA. Real power in kW is kVA times power factor. Resistive heat has a power factor near 1.0, motors and lighting ballasts run lower. So a 200 amp, 240 volt service is 48 kVA, and the kW it delivers depends on what is plugged in. The same arithmetic shows up when a home load is converted to amps, for example a 41,550 watt calculated load at 240 volts is 173.1 amps.

What transformer sits behind the service

A single home on a 200 amp service is normally one of several homes sharing a pole or pad mount transformer, so the utility sizes the transformer for the group and not for the service rating. Larger three phase services of 400 amps and more at 208 or 480 volts are fed from their own transformer. For the transformer sizes that match 400 to 4000 amp commercial services see the commercial service size chart.

How to read the numbers

These are service ratings, not loads. The actual connected load is set by the load calculation for the building, and the calculated demand is usually well below the service rating. Use the chart to check that a planned load fits a service or to find the service size for a known kVA, then confirm with a load calculation and the local utility.

Common questions

How many kW is a 200 amp service

At 240 volts single phase a 200 amp service is 48 kVA, or 48 kW at a power factor of 1.0. At 80 percent loading it is 38.4 kVA.

How many kW is a 100 amp service

A 100 amp, 240 volt single phase service is 24 kVA, or 24 kW at a power factor of 1.0. At 80 percent loading it is 19.2 kVA.

How many kW is a 400 amp service

A 400 amp, 240 volt single phase service is 96 kVA. A 400 amp, 480 volt three phase service is 332 kVA.

How do you convert service amps to kVA

Single phase kVA is amps times volts divided by 1000. Three phase kVA is amps times line to line volts times 1.732 divided by 1000.

Is kVA the same as kW

Only at a power factor of 1.0. kW is kVA times the power factor of the load.

Related pages

Sources

Free to cite with a link to this page. Always check the edition of the code your inspector enforces.

More charts

Wire ampacity chart from NEC Table 310.16
NEC Table 310.16 ampacities for copper and aluminum at 60, 75 and 90°C from 14 AWG to 2000 kcmil, with the terminal rule, small conductor limits and derating factors.
NEMA enclosure ratings chart
What NEMA Types 1, 3R, 4, 4X, 12 and the rest protect against, side by side, with the IP codes three published charts give for each and why they disagree.
Motor full load amps chart
Three phase motor full load amps from 1/2 to 500 HP at 115, 200, 208, 230, 460, 575 and 2300 V from NEC Table 430.250, single phase from 430.248, with wire, breaker and kVA by HP.
What size wire for every amp rating, 15 to 4000 amps
Wire size by amps from 15 to 400 A in copper and aluminum, the dwelling service sizes under NEC 310.12, and parallel sets for 400 to 4000 A services, with a calculator.
Primary distribution voltages, 4.16 kV to 34.5 kV
Every standard US primary voltage from 2.4 kV to 69 kV with its phase to ground value, wye or delta, insulation class and BIL, and what 12470Y/7200 on a nameplate means.
Commercial electrical service sizes, amps, kVA and transformer
Standard commercial service sizes from 100 to 4000 amps at 208Y/120 and 480Y/277 volts, the kVA each one carries, the transformer that feeds it, and when ground fault protection applies.
Breaker size chart, every standard breaker rating and its wire size
Every standard breaker size in NEC 240.6(A) from 10 to 6000 amps, the matching copper and aluminum wire size at 60 and 75°C, the 125 percent continuous load rule and common appliance circuits.
Transformer fuse size chart, primary full load amps by kVA and voltage
Primary full load amps for 25 to 2500 kVA three phase transformers at 4.16 to 34.5 kV, the NEC 450.3(B) 125 and 250 percent limits worked out at 480 V, and how pad mount fuses are chosen.
Copper bus bar ampacity chart, by bar size and temperature rise
Ampacity of 68 standard rectangular copper bus bar sizes from 1/16 by 1/2 inch to 3/4 by 12 inch at 30, 50 and 65 C rise, with area, weight and how to pick a bar for a transformer secondary.
Grounding electrode conductor size chart from NEC Table 250.66
NEC Table 250.66 grounding electrode conductor sizes in copper and aluminum, the 6 AWG rod rule and 4 AWG concrete encased rule, and the ground wire size for 100, 200, 400, 600, 800 and 1200 amp services.
How many acres does 1 MW of solar need
A utility scale solar farm needs about 5 to 10 acres per MWac. Fixed tilt averages 7.6 acres and single axis tracking 8.7 acres, with a table from 1 to 500 MW, panel counts and step up transformers.
Generator kVA to kW and amps chart
Generator kVA to kW and full load amps for 10 to 3,000 kVA at 120/240, 208, 240, 480, 600, 2,400 and 4,160 volts, computed at 0.8 power factor, with kW to kVA at other power factors.
Service wire size chart
Service entrance wire size for 100, 125, 150, 200, 225, 320, 400 and larger services in copper and aluminum, with the NEC 310.12 dwelling rule, parallel sets to 2000 amps, ground wire and the transformer behind the service.
NEMA plug and receptacle chart
NEMA plug chart for every straight blade and locking configuration, with voltage, poles, wires, amp ratings, the 80 percent continuous limit, how to read a name like 14-50R and L6-30P and which series fits 120, 208, 240 and 480 volts.
AWG wire gauge chart with diameter, mm2, kcmil and resistance
American wire gauge chart from 4/0 to 40 AWG with diameter in inches and mm, area in mm2 and kcmil, and copper resistance, plus a kcmil to mm2 table from 250 to 2000 kcmil.
CallGet a quote